§ 285.816. What must I do if environmental or other conditions adversely affect a cable, pipeline, or facility?
70 words·~1 min read·
/us/cfr/t30/s§ 285.816·A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
If environmental or other conditions adversely affect a cable, pipeline, or facility so as to endanger the safety or the environment, you must:
(a)Submit a plan of corrective action to BSEE within 30 days of the discovery of the adverse effect.
(b)Take remedial action as described in your corrective action plan.
(c)Submit to the BSEE a report of the remedial action taken within 30 days after completion.